The chart below outlines the Custom Incentive Program process.
|
Step |
Customer |
PPL Provides |
|
Application |
Estimate Savings Calculations |
Possible Site Visit |
|
Develop Commissioning Report |
|
Submit Custom Incentive Application |
|
Commissioning |
Install measures |
Approval Agreement |
|
Verify savings according to commissioning plan |
|
Notification |
Submit Project Completion Form |
Possible Site Visit |
|
Incentive Check | |
-
Submit a Custom Measure Incentive Application with Commissioning Plan. All custom incentive applications will be reviewed individually to determine eligibility. A site visit may be required to further evaluate calculations, assumptions, facility descriptions, and savings estimates.
-
Install Measures and Perform Commissioning. If approved, install the energy saving measures at the facility.
-
Post Installation Inspection and Payment: Notify PPL Electric Utilities when the project is complete. We may schedule an inspection and may adjust the incentive amount depending on the results of the project. After the review and approval of the Commissioning Report and verification of installation and compliance, PPL Electric Utilities will process the incentive payment within six weeks.
|
|
|
|
|
|
|
Click here for a list of measures with fixed E-power rebate amounts that would not qualify for a custom rebate but that you may want to apply for based on certain recommended energy efficiencies. | |