Complete List of Changes

Rules for Electric Meter and Service Installations (REMSI)


Print this list

Customer Reference Specifications-List of Changes: 2017, 2016, 2015, 2014, 2012, 2011
Complete List of Changes for Sketches: 201620152014 20132012, 2011
REMSI Rules - List of Changes:  2017, 2015, 2014, 2013, 2012, 2011
Definitions - List of Changes: 2011
Approved Metering and Equipment Tables-List of Changes: 2017201620152014, 2013, 2012, 2011

SKETCH NOTES
NOTE "PPL" and "Company" will be changed to "PPL EU", "PPL's" and "Company's" will be changed to "PPL EU's".
NOTE 1 All updated sketches have been redrawn for clarity using a new format.

NOTE 2

The 3 phase, 4 wire, 240-single phase 120/240 volts service is now referred to as 3 Phase, 4 Wire, Delta 240/120 Volts.
NOTE 3 Are changing the terms ' meter trough' to 'meter base' and 'meter mounting' to 'meter panel'.

 

Sketch # 2016 Changes, Updates and Additions
3 

09/19/2016:

  • Removed requirement for Approval of Metering Services
  • Updated Table A
  • Updated max tension to 850lbs
4 09/19/2016 - Added note that structure must be installed in an area which is not accessible to vehicular traffic.
5  09/19/2016 - Updated max tension to 850 lbs.
6  09/19/2016 - Updated max tension to 850 lbs.
14  09/19/2016 - Updated layout and added bonding jumper size to notes.
14A  09/19/2016 - Updated layout and added bonding jumper size to notes.
14B 09/19/2016 - Updated layout and added bonding jumper size to notes.
14C 09/19/2016 - Updated layout and added bonding jumper size to notes.
14D 09/19/2016 - Updated layout and added bonding jumper size to notes.
15  09/19/2016 - Updated layout and added bonding jumper size to notes. 
15A 09/19/2016 - Updated layout and added bonding jumper size to notes. 
25  09/19/2016 - Corrected diagram of 2 Wire, 1 Phase, 120V meter base
30 

09/19/2016:

  • Updated minimum pole class from 4 to 3
  • Updated Note 3 on Point of Contact requirements
31

09/19/2016:

  • Updated minimum pole class from 4 to 3
  • Updated Note 3 on Point of Contact requirements
32

09/19/2016:

  • Removed metering equipment from Sketch
  • Removed "outdoor metering equipment" from title
33 

09/19/2016:

  • Updated metering equipment in Sketch
  • Updated Note 1 on Point of Contact requirements
34 

09/19/2016:

  • Updated metering equipment in Sketch
  • Updated Note 1 on Point of Contact requirements
39

09/19/2016:

  • Removed fused interrupter requirement in Note 3
  • Added Note 6
47 

09/19/2016:

  • Updated Sketch to include class 3, 4, and 5 poles
  • Updated layout
48  09/19/2016 - Minor updates to sketch
50  09/19/2016 - Updated clearance from the bus work to front of cabinet from 1" to 1.5"
54  09/19/2016 - Updated Note 5 & 6 
54A  09/19/2016 - Updated Note A 
56 

09/19/2016:

  • If a neutral connection exists at the inverter, the inverter neutral shall be connected to the service neutral
  • Customer shall contact PPL EU prior to any new installations depicted in this sketch
56A 

09/19/2016:

  • If a neutral connection exists at the inverter, the inverter neutral shall be connected to the service neutral
  • Customer shall contact PPL EU prior to any new installations depicted in this sketch
57 

09/19/2016:

  • If a neutral connection exists at the inverter, the inverter neutral shall be connected to the service neutral
  • Customer shall contact PPL EU prior to any new installations depicted in this sketch
57A

09/19/2016:

  • If a neutral connection exists at the inverter, the inverter neutral shall be connected to the service neutral
  • Customer shall contact PPL EU prior to any new installations depicted in this sketch
58 

09/19/2016:

  • If a neutral connection exists at the inverter, the inverter neutral shall be connected to the service neutral
  • Customer shall contact PPL EU prior to any new installations depicted in this sketch 
58A 

09/19/2016:

  • If a neutral connection exists at the inverter, the inverter neutral shall be connected to the service neutral
  • Customer shall contact PPL EU prior to any new installations depicted in this sketch 
59 

09/19/2016:

  • If a neutral connection exists at the inverter, the inverter neutral shall be connected to the service neutral
  • Customer shall contact PPL EU prior to any new installations depicted in this sketch 
59A 

09/19/2016:

  • If a neutral connection exists at the inverter, the inverter neutral shall be connected to the service neutral
  • Customer shall contact PPL EU prior to any new installations depicted in this sketch
59B 

09/19/2016:

  • If a neutral connection exists at the inverter, the inverter neutral shall be connected to the service neutral
  • Customer shall contact PPL EU prior to any new installations depicted in this sketch 
60

09/19/2016:

  • Updated sketch and Notes 1, 7, 8, & J
  • Added Note K
61 

09/19/2016:

  • Updated sketch and notes 2, 8, 9, & J
  • Added Note K
70

09/19/2016:

  • Updated sketch and Notes 2, 5, 10, 13, & D
  • Added Note E
71

09/19/2016:

  • Updated Note 1
  • Added Notes J & K
  • Changed voltage from single phase 277/480 volts to single phase 240/480 volts
72

09/19/2016:

  • Updated sketch and Notes 1, E, F, & N
  • Added Note O
73 

09/19/2016:

  • Updated Notes 1, 4, 5, 7, & I
  • Added Note J
  • Changed voltage from single phase 277/480 volts to single phase 240/480 volts
80 

09/19/2016:

  • Updated sketch and Notes 1, 4, 5, 6, B, & I
  • Added Note J
81

09/19/2016:

  • Updated sketch and Notes 2, 6, 7, B, & I
  • Added Note J
82 

09/19/2016:

  • Updated Notes 1, 3, 4, 6, & I
  • Added Note J
83 

09/19/2016:

  • Updated sketch and Notes 1, 4, 5, B, & I
  • Added Note J
90 09/19/2016 - Added new Sketch on single phase outdoor metering equipment on customer-owned meter pole 

 

Sketch # 2015 Changes, Updates and Additions
3  08/11/2015 - Added note "Requires Approval from Supervisor - Metering Services".
3B  07/15/2015 - Added note "Requires Approval from Supervisor - Metering Services".
53 07/15/2015 - Minimum width of mounting surface changed from 16" to 36".
7 04/10/2015 – Note 5 updated to be furnished and installed by the customer and maintained by PPLEU. This is the service lateral conduit to the 90 degree elbow.
15A 04/10/2015 – Labeled the voltage transformers on the drawing, Note 8 not needed. Note 9 was moved to Note 8.

 

Sketch # 2014 Changes, Updates and Additions
7A 03/13/2014  Clarified dimensions of required weep holes in Notes E and F.  
23 03/7/2014Removed bus bar hole size requirement and clarified notes concerning CTs. Expanded the sketch to two sheets.
30  03/4/2014 – Sketch bifurcated into two sheets to separate notes from the sketch. Updated sketch to new format. New note added to drawing limiting customer fusing to 175E standard speed power fuses.
31 03/4/2014 – Sketch bifurcated into two sheets to separate notes from the sketch. Updated sketch to new format. New note added to drawing limiting customer fusing to 175E standard speed power fuses.
32 03/4/2014 – Sketch bifurcated into two sheets to separate notes from the sketch. Updated sketch to new format. New note added to drawing limiting customer fusing to 175E standard speed power fuses.
33 03/4/2014 – Sketch bifurcated into two sheets to separate notes from the sketch. Updated sketch to new format. New note added to drawing limiting customer fusing to 175E standard speed power fuses.
34 03/4/2014 – Sketch bifurcated into two sheets to separate notes from the sketch. Updated sketch to new format. New note added to drawing limiting customer fusing to 175E standard speed power fuses.
35 03/4/2014 – Sketch bifurcated into two sheets to separate notes from the sketch. Updated sketch to new format. New note added to drawing limiting customer fusing to 175E standard speed power fuses.
36 03/4/2014 – Sketch bifurcated into two sheets to separate notes from the sketch. Updated sketch to new format. New note added to drawing limiting customer fusing to 175E standard speed power fuses.
38 03/4/2014 – Sketch bifurcated into two sheets to separate notes from the sketch. Updated sketch to new format. New note added to drawing limiting customer fusing to 175E standard speed power fuses.

 

Sketch # 2013 Changes, Updates and Additions
16  09/27/13 - General updating for clarity, changed location of VT rack and bonding.
16A  09/27/13 - General updating for clarity, changed location of VT rack and bonding.
16B 09/27/13 - Sketch eliminated. Installations with sixteen conductors per phase no longer allowed.
25A 06/07/13 – Expanded the sketch to two sheets. Added a sub-sketch for two-wire 120 volt service at the bottom of sheet 2.

return to top

Sketch # 2012 Changes, Updates and Additions
27 10/11/12 - Updated format and content.
28 10/11/12 – Updated format and content.  Added sub-sketch for barriers in driveway areas.
47  10/11/12 – Corrected spellings and pole setting depths. 
73 10/11/12 – Corrected title and note H to remove references to 240/480 volts. 
35 NOTE:  Requires Approval by Supervisor of Metering Services is now replaced with NOT FOR NEW CONSTRUCTION -- Drawing not updated!
10/12/12 Added verbiage in red to Distributed Generation Organization Map
Customer shall contact PPL EU prior to any new installations depicted in these sketches.
07/12/12 Added verbiage in red to Distributed Generation Organization Map below:
Distributed Generation Organization Map

If a neutral connection exists at the inverter, the inverter neutral shall be connected to the service neutral.  As part of future review of all DG sketches, the above verbiage will be added to each sketch.
Metering Type Voltage Load Center Bus Bar Rating Sketch #
Self-Contained Less than 480 V Up to and Including 20% 56
Over 20% 56A
480V Self-Contained 480 V Up to and Including 20% 57
Over 20% 57A
CT/Secondary Less than 600 V Up to and Including 20% 58
Over 20% 58A
12 kV 12 kV Pole Mount Up to and Including 20% 59
Over 20% 59A
Switchgear All Options 59B

return to top

Sketch # 2011 Changes, Updates and Additions
3B 03/18/11 Updated Format and Content
7 03/18/11 Updated Format and Content
7B 03/18/11 New Sketch
8C 08/12/11 Updated Format & Content
8D 08/12/11 New Sketch
Sketch 16 Series - Sketch 16A has been revised, reformatted and updated into a series of sketches:
  • Sketch 16 - up to and including 2000A - 8 conduits
  • Sketch 16A - up to and including 3000A - 12 conduits
  • Sketch 16B - up to and including 4000A - 16 conduits
20 08/12/11 New Sketch
49 08/12/11 Updated Title & Format
54A 08/12/11 Updated Title & Format
55 08/12/11 Updated Format & Content
Distributed Generation Sketch Series have been updated, expanded and renumbered for organization. Each sheet has had content updated or in new. The new Distributed Generation Series is as follows:
Distributed Generation Organization Map
Metering Type Voltage Load Center Bus Bar Rating Sketch #
Self-Contained Less than 480 V Up to and Including 20% 56
Over 20% 56A
480V Self-Contained 480 V Up to and Including 20% 57
Over 20% 57A
CT/Secondary Less than 600 V Up to and Including 20% 58
Over 20% 58A
12 kV 12 kV Pole Mount Up to and Including 20% 59
Over 20% 59A
Switchgear All Options 59B

return to top

List of Changes - Customer Reference Specifications
2017 Changes to CRS's are:

6-10-165 – Requirements for Service to Customer-Owned Street Lighting Systems Served Under Rate Schedule SE

Effective 09/25/2017 – Identification – Added note requiring addition of number (2) and CID 323301 for 2 inch wide, yellow and black diagonal striped, pressure sensitive adhesive tape.

6-17-122 – Customer Installed Three-Phase Pad-mounted Precast Transformer Foundation

Effective 03/27/2017 – “All protective barriers must be removable bollards (constructed as or equivalent to 6-17-122G)” in Note 13. Updated 6-17-122-G as removable bollard.

6-22-187 – Install Three-Phase, 200 A Switchgear Foundation

Effective 03/27/2017 Below are the updates:

  • Added “All protective barriers must be removable bollards (constructed as or equivalent to 6-22-187E-B)” in Note 10
  • Revised 6-11-187E into 6-22-187E-A and 6-22-187E-B
  • Updated 6-22-187E-B as removable bollard

6-22-197 – Install Three-Phase, 600 A Switchgear Foundation

Effective 03/27/2017 Below are the updates:

  • Added “All protective barriers must be removable bollards (constructed as or equivalent to 6-22-197E-B)” in Note 10
  • Revised 6-22-197E into 6-122-197E-A and 6-22-197E-B
  • Updated 6-22-197E-B as removable bollard

6-22-198 – Ultra Service Park Precast Concrete Foundation

Effective 03/27/2017 Below are the updates:

  • Added “All protective barriers must be removable bollards (constructed as or equivalent to 6-22-198E-B)” in Note 10
  • Revised 6-22-198E into 6-122-198E-A and 6-22-198E-B
  • Updated 6-22-198E-B as removable bollard

6-09-192 – 12kV 3-Phase Service Interrupter Switch on Customer-Owned Pole (Overhead Supply to Underground)

Effective 01/16/2017.  Below are the updates:

  • Renamed section from "Customer Reference Specification - 12kV 3-Phase Service Fused Interrupter Switch on Customer-Owned Pole" to "Customer Reference Specification - 12kV 3-Phase Service Interrupter Switch on Customer-Owned Pole (Overhead Supply to Underground)"

  • Added statement on referring to CRS 6-09-199

  • Replaced Note 9 on fuse sizing with reference to Point of Contact document

  • Added Note 10 for switch handle requirements

  • Added Note 11 for requirements for Customer Main Switch

  • Updated BOM

6-09-194 – 12kV 3-Phase Service Interrupter Switch on Customer-Owned Pole (Overhead Supply to Overhead)

Effective 01/16/2017. Below are the updates:

  • Renamed section from "Customer Reference Specification - 12kV 3-Phase Service Fused Interrupter Switch on Customer-Owned Pole" to "Customer Reference Specification - 12kV 3-Phase Service Interrupter Switch on Customer-Owned Pole (Overhead Supply to Overhead)"
  • Added statement on referring to CRS 6-09-196 and 6-09-197
  • Replaced Note 10 on fuse sizing with reference to Point of Contact document
  • Added Note 11 for requirements for Customer Main Switch
  • Updated BOM

 6-09-195 – 7.2kV Single Phase Service Interrupter Switch on Customer-Owned Pole (Overhead Supply to Overhead or Underground)

Effective 01/16/2017. Below are the updates:

  • Renamed section from "Customer Reference Specification - 7.2kV Single Phase Service Fused interrupter Switch & Metering on Customer-Owned Pole" to "Customer Reference Specification - 7.2kV Single Phase Service Interrupter Switch on Customer-Owned Pole"
  • Added statement on referring to CRS 6-09-200
  • Replaced Note 9 on fuse sizing with reference to Point of Contact document
  • Added Note 10 for switch handle requirements
  • Added Note 11 for requirements for Customer Main Switch
  • Updated BOM

6-09-196 – 12kV 3-Phase Service Metering on Customer-Owned Pole (Overhead Supply to Overhead)

Effective 01/16/2017. Below are the updates:

  • Added "(Overhead Supply to OH)" to section title
  • Added statement on referring to CRS 6-09-194
  • Added Note 5 on reference to Point of Contact document
  • Updated phase to phase minimum clearance in Figure 6-09-196-A from 18" to 13"
  • Updated metering equipment position in Figure 6-09-196-B from source side to load side
  • Updated CTs and PTs position in Figure 6-09-196-C

6-09-197 – 12kV 3-Phase Service Metering on Customer-Owned Pole (Overhead Supply to Underground)

Effective 01/16/2017. Below are the updates:

  • Added "(Overhead Supply to UG)" to section title
  • Added statement on referring to CRS 6-09-194
  • Added Note 8 on reference to Point of Contact document
  • Updated BOM
  • Updated Figures 6-09-1979-A, B, & C

6-09-199 – 3-Phase, 4 Wire WYE 7,200/12,470V Service Termination and Metering Compartments in Customer Owned Switchgear

Effective 01/16/2017. Below are the updates:

  • Removed "Installation Instructions for" from section title
  • Changed "service entrance fused disconnect to "service entrance disconnect" in Note 1
  • Removed junction box from Note 10. BOM, and Figure 6-09-199-B
  • Added maximum conductors per phase per bus bar in Note 7
  • Corrected phase reference from "8" to "B" in Note 15
  • Updated page references for Point of Contact document in Note 15
  • Replaced Note 20 on fuse sizing with reference to Point of Contact document

6-09-200 – 7.2kV Single Phase Service Metering on Customer-Owned Pole (Overhead Supply to Overhead or Underground)

  • 01/16/2017 Added New Section
6-10-165 – Requirements for Service to Customer-Owned Street Lighting Systems Served Under Rate Schedule SE

Effective 01/02/2017. Below are the updates:

  • Support and support bracket Note 1: Changed minimum Class 5 to minimum of Class 3
  • General Note 1:  removed NEC reference
  • General Note 11: added customer owned structures
  • Specific Note 4: removed #TRON- from Bussman P/N
  • Customer Responsibilities Note 5: removed #TRON- from Bussman P/N
  • Figure 6-10-165-C, set to Not for New Construction"
  • Figure 6-10-165-D, removed "Not for New Construction" from Figure
  • Figure 6-10-165-C & D, Customer Responsibilities Note 5: removed the NEC reference
  • Revised Pole to Class 3 from Class 5 in Support and Support Bracket notes
  • Added Note 19 to General Notes Section
  • Added Note 6 to Specific Notes:  Power Supply & Equipment Figures 6-10-165-A and 6-10-165-B Section
          

return to top

List of Changes - Customer Reference Specifications
2016 Changes to CRS's are:

6-14-121 - Requirements for Trenching and Backfilling by Developer/Customer for Primary and Secondary Installation in a Trench with Only Electric Lines (Non-Joint Trench)
Underground - General Specifications

Effective 12/05/2016. Below are the updates:

  • Clarified that non-joint trench is without gas lines
  • Changed "contractor" to "customer"
  • Changed "fish line" to "pulling line"
  • Added line "Customer muct dig trench on their own property or will be subject to additional charges in Note 5

6-14-122 - Requirements for Trenching and Backfilling by Developer/Customer for Primary and Secondary Installation in a Trench with Electric and/or Gas, Telecommunication Lines (Joint Trench)
Underground - General Specifications

Effective 12/05/2016. Below are the updates:

  • Changed "trench with electric and/or gas, telecommunications lines" to "trench with electric and gas and possibly telecommunications lines"
  • Changed "fish line" to "pulling line"
  • Indicated all conduits muct be 45 inches deep in Note 8-B
  • Added line "Customer must dig trench on their own property or will be subject to additional charges" in Note 5

6-14-125 - Customer-Installed Screening of Pad-mounted Devices
Underground - General Specifications

Effective 12/05/2016. Below are the updates:

  • Changed "landscape architect" to "PPL EU"
  • Additional instruction "DO NOT COVER TRANSFORMER"

6-15-160 – Customer Installed Precast Manhole

  • 07/11/2016 Replaced with this spec from 10/30/2015, the one posted on site was from 11/15/2012. Below are the updates:
    • Customer is responsible to install PPL Standard equipment per PPL Specification
    • Pulling lines should only be used to enable installing adequate rope
    • Drawings updated to include locking manhole cover
    • Updated loading rating to H-25

return to top

List of Changes - Customer Reference Specifications
2015 Changes to CRS's are:

6-19-100 – Customer Low-Voltage Switchboards Service Cable Terminal Compartment Arrangements and Clearances

  • 07/27/2015 Replaced with this spec from 3/31/2015, the one posted on site was from August of 2013. 

6-09-196 – 12kV 3-Phase Service Metering on Customer-Owned Pole. Overhead Supply to Overhead

  • 04/10/2015 Bill of Material item #3 moved to Material Supplied by Customer and changed to a minimum class size 3 pole. Updated items 13, 14 and 15.

6-09-197 – 12kV 3-Phase Service Metering on Customer-Owned Pole. Overhead Supply to Underground

  • 04/10/2015 Bill of Material item #3 changed to a minimum class size 3 pole.
6-15-160 – Customer Installed Precast Manhole
  • 04/23/2015 Revised to follow Distribution Construction Specification formatting - Effective Date: 11/15/2012. Previous update 05/02/2005.
6-15-180 – Customer Installed Duct System
  • 04/23/2015 Revised to follow Distribution Construction Specification formatting - Effective Date: 11/15/2012. Previous update 03/19/2010.

6-19-133 – Installation of 120/240 Volt Single-Phase Underground Lateral Sharing a Trench with Other Utilities (Joint Trench)

  • 04/10/2015 Service lateral conduit up to the 90 degree elbow is now furnished and installed by the customer and maintained by PPLEU. (This is shown in Figure 6-19-133-A and figure Notes 7 and 8.)

6-19-134 – Requirements for Trenching and Backfilling by Customer for 120/240 V Underground Service Laterals Installation in a Trench with only Electric Lines (Non-Joint Trench)

  • 04/10/2015 Service lateral conduit up to the 90 degree elbow is now furnished and installed by the customer and maintained by PPLEU. (This is shown in Figure 6-19-134-A and figure Notes 6 and 7.)

return to top

List of Changes - Customer Reference Specifications
2014 Changes to CRS's are:
 6-10-165 – Requirements for Service to Customer-Owned Street Lighting Systems Served Under Rate Schedule SE
  • 10/31/2014 Additional Notes were added to Specific Notes: “preferred method for fusing underground served lighting and is the required method for new installation in which two or more lights are served from a single point of delivery where the junction box will not be surrounded by concrete”,  on page 88 of 98
    • Addition to Sketch 6-10-165 G a Side View perspective of Zones A - D on page 96 of 98 and
    • Addition of Sketch 6-10-165 H a Front View perspective of Zones A - D on page 97 of 98
  • 01/15/2014 Additional Notes were added to sketches 6-10-165A & B for clarification.
 6-19-100 – Customer Low-Voltage Switchboards Service Cable Terminal Compartment Arrangements and Clearances
  • 08/30/2013 General revision and updated to new document format
 6-19-133 – Installation of 120/240 Volt Single-Phase Underground Lateral Sharing a Trench with Other Utilities (Joint Trench)
  • 08/30/2013 General revision and updated to new document format. Clarified wording for customer’s requirements and responsibilities. Updated the drawings.
 6-19-134– Requirements for Trenching and Backfilling by Customer for 120/240 V Underground Service Laterals Installation in a Trench with only Electric Lines (Non-Joint Trench)
  • 08/30/2013 General revision and updated to new document format. Clarified wording for customer’s requirements and responsibilities. Updated the drawings.

return to top


List of Changes - Customer Reference Specifications
2012 Changes to CRS's are:
6-09-100 12kV 3-Phase Service – Electronic Controlled Recloser – On Customer Owned Pole
  • 7/25/2012 Added to Customer Reference Specifications dated 6/25/2008
6-10-165 Outdoor Lighting - Requirements for Service to Customer-Owned Street Lighting Systems Served Under Rate Schedule SE
  • 10/31/11 Sheet 1-16
    • Updated wordings of general notes and updated numbers in Sheets 2 and 3.
    • Updated last paragraph in Sheet 4.
    • Updated sheet numbers in Sheet 5.
    • Updated figure and sheet number in Sheet 6.
    • Updated last paragraph and figures number on Sheet 7.
    • Updated sheet numbers in Sheet 8.
    • Updated figure and sheet number in Sheet 9.
    • Updated diagram label in Sheet 10.
    • Updated diagram label in Sheet 11.
    • Updated diagram clearance in Sheet 12.
    • Updated figure number and updated diagram in Sheet 13.
    • Updated diagram label and dimensions. Updated format in Sheet 15.
    • Updated figures, number and fonts.

return to top


List of Changes - Customer Reference Specifications
2011 Changes to CRS's are:
6-09-194 Overhead Service to Overhead
  • 09/08/11 Sheet 1
    • Made into formal title page, content now starts on Sheet 2.
    • Added statement, specifying CRS 6-09-194 is part of the Rules for Electric Meter and Service Installation (REMSI) Website.
  • 09/08/11 Sheet 2
    • Split Note 1 into Note 1 and 2.
    • Re-numbered notes accordingly.
    • Updated new Note 4 - ground wire comes from the lightning arrestor cross arm.
  • 09/08/11 Sheet 3
    • Updated Bill of Material to meet current requirements.
  • 09/08/11 Sheet 4
    • Updated Bill of Material to meet current requirements.
  • 09/08/11 Sheet 5
    • Updated drawing notes to match Bill of Material changes.
  • 09/08/11 Sheet 6
    • Updated drawing notes to match Bill of Material changes.
  • 09/08/11 Sheet 7
    • Metering Compartment Drawing - added references to Note 18 and Note 19.
    • Removed Detail B. Terminal block is to be attached to neutral bar; previously terminal block was attached to the side of the termination compartment.
    • Updated minimum working clear space in front of metering compartment to 9' 0" from 5' 0".

6-09-199 Installation Instructions For 3-Phase, 4 Wire WYE 7,200/12,470V Service Termination and Metering Compartments in Customer-Owned Switchgear

09/08/11 Sheet 5

Bill of Material item 3 updated.

09/08/11 Sheet 7

Updated drawing - VT's to be mounted on shelf instead of on back of metering compartment.

6-14-121 Requirements for Trenching and Backfilling by Developer/Customer for Primary and Secondary Installation in a Trench with Only Electric Lines (Non-Joint Trench)
  • 09/08/11 Sheet 1
    • Updated title.
    • Made into formal title page, content now starts on Sheet 2.
    • Added statement, specifying CRS 6-14-121 is part of the Rules for Electric Meter and Service Installation (REMSI) Website.
  • 09/08/11 Sheet 2
    • Added reference to CRS 6-15-180.
    • Updated information in Note 2.
  • 09/08/11 Sheet 4
    • Added flow-able fill as a select backfill option
  • 09/08/11 Sheet 5
    • Notes expanded to Sheet 5, all pages from this point forward were renumbered accordingly.
  • 09/08/11 Sheet 6
    • Updated drawing notes and added more detail on dimensions.
  • 09/08/11 Sheet 7
    • Updated drawing for content and clarity.
6-14-122 Requirements for Trenching and Backfilling by Developer/Customer for Primary and Secondary Installation in a Trench with Electric and/or Gas, Telecommunication Lines (Joint Trench)
  • 09/08/11 Sheet 1
    • Updated title.
    • Made into formal title page, content now starts on Sheet 2.
    • Added statement, specifying CRS 6-14-122 is part of the Rules for Electric Meter and Service Installation (REMSI) Website.
  • 09/08/11 Sheet 2
    • Added reference to CRS 6-15-180.
    • Updated information in Note 2.
  • 09/08/11 Sheet 4
    • Added flow-able fill s a select backfill option.
  • 09/08/11 Sheet 5
    • Notes expanded to Sheet 5, all pages from this point forward were renumbered accordingly.
  • 09/08/11 Sheet 6
    • Updated drawing notes and added more detail on dimensions.
  • 09/08/11 Sheet 7
    • Updated drawing for content and clarity.
  • 09/08/11 Sheet 8
    • Updated drawing for content and clarity.
  • 09/08/11 Sheet 9
    • Updated drawing for content and clarity.

return to top

 

List of Changes - REMSI RULES - 2017

Rule 5 - 12/8/2017

  • Updated wording under g. Conductor(s) with Higher Voltage to Ground for 3 Phase, 4 Wire, 120/240 Volt Delta Service.  In the first paragraph 'instrument transformer cabinet (CT cabinet)' was added.  In the second paragraph 'self-contained' was added as well as the last sentence in the paragraph.

return to top

List of Changes - REMSI RULES - 2015

Rule 2 – 5/20/15

  • Removed 120/240V 4-wire delta from “Standard Service Voltages and placed under “Non-Standard Service Voltages”.
  • Removed 480V 3-wire delta from “Standard Service Voltages” and placed under “Non-Standard Service Voltages”.
  • Reworded notes 4 and 5.

return to top

List of Changes - REMSI RULES - 2014
Rule 19 – 12/11/14 Section B, added list of when an electrical inspection is required.

Rule 15 – 2/27/14 Section E, Switchgear, changed screen door to height door(s).

Rule 7 – 2/10/14 – Section E, added statement about 175E fusing.
Rule 8 – 2/10/14 – Section A (3), added statement about 175E fusing.

return to top

List of Changes - REMSI RULES - 2013
Rule 2 – 6/26/13 – Under note 4, removed sentence: “Delta served load shall be limited to those loads which can be provided by an open Wye-open delta transformer bank”.
Rule 3 – 6/26/13 – Under section d, added sentence: "Customer owned transformer banks configured as grounded wye primary and closed delta secondary shall not be connected to the PPL EU system without prior approval from PPL EU".
Rule 1 – 3/18/13 – Replaced “h” 2nd paragraph with “The customer pays the fully allocated cost of any primary or secondary facilities needed to serve the additional points of delivery”.
Rule 19 – 3/18/13 – Added to “b” 3rd paragraph 1st sentence “Inspection cut-in cards must be received at the local PPL EU office before any service request job can be scheduled”.
Rule 2 – 2/5/13 – Removed wording from Note 4, “On underground residential distribution services”.
Rule 16 – 2/5/13 – Section F – added conditions for PPL EU to waive the requirement for a termination compartment.

return to top

List of Changes - REMSI RULES - 2012
Rule 2 – 10/11/12 – Revised rule 2c (residential service), requiring approval for voltages above 120/240 and requiring instrument transformers for the higher voltages.
Rule 5 – 10/11/12 – Revised rule 5g, specifying where to connect high leg conductors in instrument transformer cabinets.

return to top

List of Changes - REMSI RULES - 2011
Rule 1 - 7/29/11
  • Edited Rule 1h
  • Added Rule 1i
  • Re-lettered rule accordingly
Rule 2 - 3/4/11
  • Section B added, following sections re-lettered.
  • Sections E and F (Formerly D and E) revised.
  • Note 6 Revised.
Rule 6 - 10/26/11
  • Section B title Updated
  • Section C title Updated, added last two paragraphs detailing rear lot service requirements
Rule 11B - 10/26/11 Section E - added last paragraph detailing rear lot service requirements
Rule 12 - 7/29/11 Added Section j - Grounding

3/4/11 Section f revised.
Rule 13 - 10/26/11
  • Section B - added exception meter height in flood area
  • Section C - added exception indoor location in flood area
Rule 15 - 8/12/11 Updated to include Sketch #8D and Sketch 16 Series

3/4/11 Corrected terminology
Rule 18 - 8/12/11 

Updated to include Sketch #8D and Sketch 16 Series

Rule 19 - 10/26/11 Section G added, re-lettered Cut-In Card Documents to Section H

7/29/11
  • Updated Section b
  • Inserted Section c - Inspection Exemption - Ralroad Not Covered in NEC
  • Re-lettered rule accordingly
  • Updated Cut-In-Cards
Rule 25A - Updated wording in 25A(a)(1) to remove requirement of installation and annual maintenance fees on demand pulse contracts.

return to top


List of Changes - Definitions - 2011
10/26/11 Added/revised the following definition:
  • Roadway

3/4/11 Added/revised the following definitions:

  • Current Transformer Mounting Bridge
  • Foreign Energy Source
  • Junction Box
  • Metering Equipment
  • Point of Interconnection
  • Renewable Energy Source
  • Service Termination Compartment

return to top

 

Approved Metering and Equipment Tables-List of Changes - 2017
 12/12 Removal of Metering Types from Approved Meter Service Devices from:  

Tables 1, 2, 3, 4, 8, and 9 – 600 Amps (CI 480) (Bolt-in metering)

Table 3, 4: Removal of Note 9 – Class 480 Meter Bases
11/16 Approved Automatic Transfer Switches - Added new Automatic Transfer Switches - Closed Transition Make-Before-Break
11/15 Added New List of Manufacturers and Model Numbers to the Solar Inverters
 
return to top

 

Approved Metering and Equipment Tables-List of Changes - 2016
08/02 Approved Automatic Transfer Switches – Added Global Power Products – GenerLink (Meter Collar) descriptions for each model number

07/26 Approved Automatic Transfer Switches – Added 071095 (DirectPower Meter Mounted) to Briggs and Stratton.

Approved Automatic Transfer Switches – Added Global Power Products – GenerLink (Meter Collar) MA 23-N, MA23-S, MA24-N, MA24-S 
04/22 Added New Equipment Table for 12kV Customer Main Switches 
02/21 Added Statement to Approved Connector List for Sketch #49

Distribution Block Connectors when used for Service Drop connections to service entrance conductors shall be covered to avoid inadvertent contact.  Except the neutral connection of service cable assemblies may be bare.

return to top

 

Approved Metering and Equipment Tables-List of Changes - 2015
09/21 Added New Equipment Table for Solar Inverters and Inverter Guide is embedded link for further explanation
09/09 Approved Meter Services Devices – Table 10 – Added ONLY to Table heading for clarity - MOBILE HOME METER PEDESTALS ONLY
05/11 Approved Switchgear Metering and Termination Compartments - 
Table 2
 – Update Square D Termination Compartment drawing # 43-0036-2203 AUX to Rev D
 
03/02

Approved Switchgear Metering and Termination Compartments -
Table 1
– Update Square D Metering Compartment drawing # 43-0036-202 APPR to Rev J

Update Square D Termination Compartment drawing # 43-0036-202 AUX to Rev F

return to top

 

 

Approved Metering and Equipment Tables-List of Changes - 2014
05/28

Approved Pad Mounted Metering and Termination Cabinets - Table 1 - Added Manufacturer and new drawing # PPL-2000A-16-3R, Rev. F

Added new Model drawing # PP-S600-16A-480 (3200A), Rev. 01 

06/06 Approved Switchgear Metering and Termination Compartments - Table 2 – Updated Square D Switchgear Drawing # 43-0036-203 APPR to Revision H
04/28 Approved Switchgear Metering and Termination Compartments - Table 3 – Updated PowerCon Switchgear Drawing # D-12560 to Revision 1

return to top

 

Approved Metering and Equipment Tables-List of Changes - 2013
12/10 Approved Automatic Transfer Switches – Added KCS series to Kohler. 
11/21 Approved Automatic Transfer Switches – Added Briggs and Stratton.
08/15 Approved Meter Services Devices – Table 5 – Milbank New Approval for ALL 5th Terminal Accessories listed.
07/31 Approved Meter Services Devices – Table 4 – Removed Eaton/Cutler Hammer 1004138A-CH, Durham 1004138A, and Square D 1004138A-SQD. All Not useable for U.G. 
05/28 Approved Pad Mounted Metering and Termination Cabinet – Table 3 – Added PPL1215 revision 9 and PULL1215 revision 5.
04/16 Approved Pad Mounted Metering and Termination Cabinet – Table 3 – Added PP-S466 revision 5. 
03/20 Approved Pad Mounted Metering and Termination Cabinet – Table 1 – Added PP-S600-16-480 revision 5. 
03/04  Approved Automatic Transfer Switches –Added KCP to Kohler 
02/20 Approved Pad Mounted Metering and Termination Cabinet – Table 1 – Added manufacturer and new drawing PP-S600-16-480.
01/25  Approved Switchgear Metering & Termination Compartments - Table 3 - Added Federal Pacific as a manufacturer. Added new drawing D38-2228-001
01/17 Approved Automatic Transfer Switches – Added (C) to indicate a change 
01/07 Approved Meter Services Devices – Table 1, 2, 3, and 4 – Added Talon (formerly Landis & Gyr) Name Change

return to top

Approved Metering and Equipment Tables-List of Changes - 2012
11/12

Approved Meter Services Devices - Table 5 - Added Talon (formerly Landis & Gyr) New Design (Catalog# UA3B11-0PZA)

Approved Meter Services Devices - Table 7 - Added Siemens WP and WPL Series

Approved Meter Services Devices Table 11 - Added Talon (formerly Landis & Gyr) New Model (Catalog# LG0816B1400RLT) and Siemens New Model (Catalog# MM0202S1200RJB)

06/28 Approved Switchgear Metering & Termination Compartments - Table 3 - Added Park as a manufacturer. Added new drawing PPL-1

Updated Square D Drawings UTL-00000-00001 Issued Revision D.
Updated Square D Drawings UTL-00000-00004 Issued Revision C.
Updated Square D Drawings UTL-00000-00005 Issued Revision C.
Updated Square D Drawings UTL-00000-00007 Issued Revision C.
Updated Square D Drawings UTL-00000-00010 Issued Revision C.
Updated Square D Drawings UTL-00000-00001 Issued Revision C.

Added new drawing to Square D UTL-00000-00013.
06/05  Approved Switchgear Metering & Termination Compartments-Tables 1 & 2 - Issued Revision 14 for Eaton/Cutler Hammer, Drawing # 42C1054. 
05/03 Approved Meter Services Devices-Table 9 – Added 400 AMP Catalog # for Cutler Hammer 37MM140R1240 and 37MM240R1240
01/05 Approved Meter Services Devices-Table 11 – Revised Catalog # for Midwest, R-100C with MSBN1A and RS 250C with MSBN1A.  Added New Model R-102CB2 with MSBN1A

return to top

List of Changes - 2011 Approved Metering and Equipment Tables
04/13 Approved Meter Services Devices - Table 11 - Added Eaton to name: Eaton/Cutler Hammer. Added New Approvals Catalog #ECP511B Series, and #ECP521B Series
04/20 Approved Switchgear Metering & Termination Compartments - Table 1 - Added Eaton to name: Eaton/Cutler Hammer. Updated Drawing # 42C1054, Sheets 1, 2, Issued Revision 13
04/20 Approved Switchgear Metering & Termination Compartments - Table 2 - Added Eaton to name: Eaton/Cutler Hammer. Updated Drawing # 42C1054, Sheets 1, 2, Issued Revision 13
05/31 Approved Instrument Transformer Cabinets - Table 6 - Added PENN PANEL as a manufacturer. New catalog listing, PPL-724812
08/12 NEW TABLE - Pad Mounted Metering and Termination Compartment Table
08/12 NEW TABLE - Connector Table

return to top



11/2017