New or Upgraded Residential Service

Welcome to the neighborhood! PPL Electric Utilities looks forward to providing your electric service.

Whether building a new home or upgrading your electric service, PPL Electric Utilities is here to serve your needs. There is generally no cost for new or upgraded service, with the exception of placing power lines underground or requests to move electrical facilities from our designer’s plan. We recommend applying at least 9 weeks before your new service is needed.

family riding bikes in neighborhood

1. Application

Apply 9 weeks before you need service.

2. Design

A designer will call within a week of your application to schedule a meeting for a future date.

3. Scheduling

Jobs are typically scheduled for 6-8 weeks after design completion and all requirements have been met.

4. Construction

Timing depends on the amount of work required and the weather.

5. Billing

The customer will receive an electric bill after the meter is placed in service and associated with an account.

Download Checklist

Download

Application

PPL offers a Self-Service Work Orders tool that helps you submit and track requests for electric service work. To get started, you’ll need to register for the portal at pplelectric.com/contractors. Create and manage your work order, whether at home, the office or the job site. Track your work order with email notifications, and see what requirements are outstanding.

  • For single phase residential meter requests, please call 1-877-220-6016.
  • For developments of 5 or fewer homes, you can use our Self-Service Work Orders tool: pplelectric.com/contractors.
  • For larger developments, please work with our Business Accounts department by emailing businessaccounts@pplweb.com or calling 1-888-220-9991.
    • Each house in the development, as well as street lights, will need a separate work order. Remember that work will not begin until we have an approved plot plan. If the development layout is changed, there will be re-engineering costs.

Design

Your PPL designer will review your application and contact you within a week of submitting a completed application. Your designer will create your plan and contact you with any estimated fees.

A right-of-way agreement is required before PPL can install any new facilities that affect property such as poles, anchors, conductors, transformers, and other equipment. Right-of-way is also required if any tree cutting or trimming is necessary. A permit may also be needed to construct facilities to your property.

 

Scheduling

Work is typically scheduled 6-8 weeks after design completion and all customer requirements have been met: customer payment, rate-payer confirmation, signed right-of-way agreement, customer contract agreement and customer tree work.

Electrical inspection and trench/conduit for underground secondary/services installation must be completed 3 weeks before construction. Trench for underground primary installation should be completed 1 week before construction.

PPL schedules jobs to be completed by the week, and the exact day will vary based on weather and other circumstances.

Payments must be made by check and mailed to:
PPL Electric Utilities WAM

PO Box 419054St Louis, MO 63141-9054


Overnight payments should be made payable to PPL Electric Utilities and sent to:

Firstech
Attn:  Lockbox PFC 
12300 Olive Blvd 
Creve Coeur, MO  64141 

 

Construction

Be sure to prepare your site for PPL crews to complete the construction work. Coordinate with other utilities such as Verizon to relocate poles or other facilities that may delay PPL’s work. Remember to call 811 at least 3 business days before you dig. We ask that property lines, easements, rights-of-way, water lines, sewer lines, sprinkler systems, septic systems, septic reserve areas, well locations, and other obstacles/obstructions are staked and marked.

Checklist for Residential Service

Application

Design

Scheduling

Be sure to meet all customer responsibilities at least 6 weeks before constructions starts:

Construction