Rule 13
Rule 13 - Meters — Secondary Service — Under 600 Volts — Location
03/22/2024
-
PPL Electric's standard practice is to locate all meters outdoors.
PPL Electric requires 18 inches minimum clearance between the centerline of the meter opening and any adjacent wall. Sketch #17.
It is prohibited to recess meter bases/panels, conceal service entrance conductors, enclose meter bases/panels in boxes, or mount meter bases/panels so that the center of the meter is lower than approximately 5 feet, and plant flowers, trees and shrubs near meter bases/panels.(Working Space)
-
PPL Electric specifies the installation location for meter bases/ meter panels. Customer installs meter base/meter panel 5 feet (from centerline of meter opening) above finished grade or floor.
Exception: Meter base may be raised higher than standard 5 ft, in areas prone to flooding, with preapproval by the supervisor of Metering Services.
-
PPL Electric requires 50 inches minimum clear space in front of meter bases/panels, instrument transformer cabinets or switchgear metering compartments.
The workspace shall permit at least a 90-degree opening of metering equipment doors or panels. The installation of the metering equipment must not interfere with the opening of doors or windows.
-
Attachment Permit for Meters on PPL Electric Pole:
Metering equipment shall not be installed on a PPL Electric pole.