Master Sketch Table
Single Phase Overhead
These sketches provide rules for single-phase underground service. Specifications for overhead service are at the bottom of the page.
| SKETCH # | DESCRIPTION |
| Sketch 1 | Triplex service drop attachment on building |
| Sketch 1A | Pages 1 & 2 - Secondary service drop attachments |
| Sketch 3 | Secondary service drop attachment to a mast attached to low building to provide required clearances |
|
Secondary service drop attachment on temporary structure for construction |
|
|
Overhead secondary service drop attachment to customer-owned service and meter pole for overhead distribution. |
|
|
Overhead secondary service drop attachment to customer-owned service and meter pole for underground distribution. 600A max. |
|
| Sketch 14a |
Typical arrangement of instrument transformers and mounting for installation in instrument transformer cabinet. Single-phase 120/240 volt or 240/208 volt, Network - 800 to 1200 ampere, single-phase 240/480 volt 600 to 800 ampere |
|
Secondary service meter base connections for self-contained meters overhead service. 100 and 200A. |
|
|
Secondary service meter base connections for self-contained meters overhead or underground service. 400A |
|
|
Multi-meter installation using meter base with factory built-in bussing |
|
|
Secondary Service Multi-Meter Installation for Common Service with Instrument Transformer Cabinets and/or Meter Bases |
|
|
Multi-meter installation for overhead service drop attachment for mobile home court |
|
|
Service drop attachment to customer-owned service and meter pole for a mobile home |
|
|
Customer wood pole |
|
|
Connectors to be provided by the customer for serving a single point of connection for multiple enclosed service entrance conductors |
|
|
Connector to be supplied by the customer for providing a single point of connection. Multiple overhead service entrance conductors. |
|
|
Clearances between gas facilities and electric meters |
|
|
Clearances between objects and electric meters |
Specs
| SPEC # | DESCRIPTION |
|
"Requirements for Service to Customer-Owned Street Lighting Systems. SE rate." |
Single Phase Underground
These sketches provide rules for single-phase underground service. Specifications for underground service are at the bottom of this section.
| SKETCH # | DESCRIPTION |
| Sketch 4A | Underground secondary service to underground attachment on temporary structure for construction |
|
Typical Arrangement of Meter on Building |
|
|
Slip riser for installation on single phase underground services |
|
|
Arrangement of instrument transformers and mounting for installation in instrument transformer cabinet |
|
|
Arrangement of outdoor meter panel on building for CT metering. Services over 600A |
|
|
Arrangement of Indoor Metering Equipment to Accommodate either Self-Contained or Secondary Instrument Transformer Metering |
|
|
Barriers for equipment installed in location with vehicular traffic |
|
|
Secondary service meter base connections for self-contained meters underground service 200A. |
|
|
Secondary service meter base connections for self-contained meters overhead or underground service. 400A |
|
|
Multi-meter installation using meter base with factory built-in bussing |
|
|
Metered traffic signal and unmetered streetlight |
|
|
Secondary Service multi-meter installation for common service with instrument transformer cabinets and/or meter bases |
|
|
Multi-meter installation for underground service lateral attachment for mobile home court |
|
|
Outdoor mobile home pedestal. Underground service lateral |
|
|
Customer wood pole |
|
|
Typical Connectors to be provided by the customer for serving a single point of connection for multiple enclosed service entrance conductors |
|
| Sketch 53 | Typical arrangement of wood post pedestal. Underground service lateral from OH or UG distribution. Single phase, 3 wire, 120/208 or 120/240 volts |
|
Termination cabinet for 1 set of cable |
|
|
Clearances between gas facilities and electric meters |
|
|
Clearances between objects and electric meters |
Specs
| SPEC # | DESCRIPTION |
|
"Requirements for Service to Customer-Owned Street Lighting Systems. SE rate." |
|
|
Primary and Secondary trench. Electric only. (non-joint trench) |
|
|
Primary and Secondary trench (joint trench) |
|
|
Placing Plants, Shrubbery or Structures around pad-mounted devices |
|
|
Installation Instructions for Customer Installed Conduit Systems on PPL Terminal Poles |
|
|
Service Trench. Electric only. (joint trench) |
|
|
Service Trench. Electric only. (non-joint trench) |
Three Phase - Overhead 208V–240V
| SKETCH # | DESCRIPTION |
| Sketch 5 |
Overhead secondary service drop attachment to customer-owned service and meter pole for overhead distribution. 600A max. |
|
Overhead secondary service drop attachment to customer-owned service and meter pole for underground distribution. 600A max. |
|
|
Meter panel installation for use in conjunction with instrument transformer metering |
|
|
Meter panel mounting arrangement for use with instrument transformer metering |
|
|
Typical arrangement of instrument transformers and mounting for installation in instrument transformer cabinet. 1200A max. |
|
|
Overhead instrument transformers and mounting for installation in instrument transformer cabinet. 2000A max |
|
|
Secondary service meter base connections for self-contained meters overhead service. 100 and 200A. |
|
|
Secondary service meter base connections for self-contained meters overhead or underground service. 400A |
|
|
Secondary Service Multi-Meter Installation for Common Service with Instrument Transformer Cabinets and/or Meter Bases |
|
|
Wiring diagram equipment used to provide demand pulses for customer use |
|
|
Customer wood pole |
|
|
Typical Connectors to be provided by the customer for serving a single point of connection for multiple enclosed service entrance conductors |
|
|
Typical connector to be supplied by the customer for providing a single point of connection. Multiple overhead service entrance conductors. |
|
|
Clearances between gas facilities and electric meters |
|
|
Clearances between objects and electric meters |
Three Phase - Underground 208V-240V
These sketches provide rules for three-phase underground (208V-240V) service. Specifications for underground service are at the bottom of this section.
| SKETCH # | DESCRIPTION |
|
Typical Arrangement of Meter on Building |
|
|
Meter panel installation for use in conjunction with instrument transformer metering |
|
|
Meter panel mounting arrangement for use with instrument transformer metering |
|
|
Instrument transformers and mounting for installation in instrument transformer cabinet. 1200A max. |
|
|
Instrument transformers and mounting for installation in instrument transformer cabinet. 2000A max. |
|
|
Pad mounted metering and service termination cabinet up to eight 750 KCMIL conductors per phase. 208V, 2000A max. |
|
|
Pad mounted metering and service termination cabinet up to twelve 750 KCMIL conductors per phase. 208V, 3200A max. |
|
|
Indoor Metering Equipment to Accommodate either Self-Contained or Secondary Instrument Transformer Metering |
|
|
Barriers for equipment installed in location with vehicular traffic |
|
|
Typical arrangement of instrument transformers in switchgear cubicle |
|
|
Secondary service meter base connections for self-contained meters underground service. 200A |
|
|
Secondary service meter base connections for self-contained meters overhead or underground service 400A. |
|
|
Secondary service multi-meter installation for common service with instrument transformer cabinets and/or meter bases. |
|
|
Structural facilities installed by customer to accommodate underground service from a 3 phase pad-mounted transformer |
|
|
Wiring diagram equipment used to provide demand pulses for customer use |
|
|
Customer wood pole |
|
|
Typical Connectors to be provided by the customer for serving a single point of connection for multiple enclosed service entrance conductors |
|
|
Typical arrangement of wood post pedestal. Underground service lateral from OH or UG distribution |
|
|
Termination cabinet for 2-6 sets of cable |
|
|
Termination cabinet for 1 set of cable |
|
|
Clearances between gas facilities and electric meters |
|
|
Clearances between objects and electric meters |
Specs
| SPEC # | DESCRIPTION |
|
Placing Plants, Shrubbery or Structures around pad-mounted devices |
|
|
Customer Installed Precast Manhole |
|
|
Customer Installed Duct System |
|
|
Customer Installed Three-Phase Pad-Mounted Precast Transformer Foundation. 75KVA to 2500KVA Capacity |
|
|
Customer Installed Transformer Vault. 30KVA to 2500KVA Capacity |
|
|
Installation Instructions for Customer Installed Conduit Systems on PPL Terminal Poles |
|
|
Customer Low-Voltage Switchboards. Service Cable Terminal Compartment. |
|
|
Installation Instructions for 3-Phase, 200 Amp Switchgear Foundation |
|
|
Installation Instructions for 3-Phase, 600 Amp Switchgear Foundation |
|
|
Three-Phase Pad-Mounted Manual or Automatic Source Transfer Switch |
|
|
PPL EU Ultra Service Park Typical Utility Plan |
Three Phase - Overhead 480V
| SKETCH # | DESCRIPTION |
|
Meter panel installation for use in conjunction with instrument transformer metering |
|
|
Meter panel mounting arrangement for use with instrument transformer metering |
|
|
Arrangement of instrument transformers and mounting for installation in instrument transformer cabinet. 1200A max. |
|
|
Arrangement of overhead instrument transformers and mounting for installation in instrument transformer cabinet. 2000A max |
|
|
Customer wood pole |
|
|
Connectors to be provided by the customer for serving a single point of connection for multiple enclosed service entrance conductors |
|
|
Connector to be supplied by the customer for providing a single point of connection. Multiple overhead service entrance conductors. |
|
|
Clearances between gas facilities and electric meters |
|
|
Clearances between objects and electric meters |
Three Phase - Underground 480V
These sketches provide rules for three-phase underground (480V) service. Specifications for underground service are at the bottom of this section.
| SKETCH # | DESCRIPTION |
|
Meter panel installation for use in conjunction with instrument transformer metering |
|
|
Meter panel mounting arrangement for use with instrument transformer metering |
|
|
Instrument transformer and mounting for installation in instrument transformer cabinet underground. 3 wire, 1200A max |
|
|
Instrument transformers and mounting for installation in instrument transformer cabinet underground service. 800A max |
|
|
Pad mounted metering and service termination cabinet up to eight 750 KCMIL conductors per phase. 2000A max. |
|
|
Pad mounted metering and service termination cabinet up to twelve 750 KCMIL conductors per phase. 3200A max. |
|
|
Barriers for equipment installed in location with vehicular traffic |
|
|
Typical arrangement of instrument transformers in switchgear cubicle |
|
|
Typical arrangement of structural facilities installed by customer to accommodate underground service from a 3 phase pad-mounted transformer |
|
|
Customer wood pole |
|
|
Typical Connectors to be provided by the customer for serving a single point of connection for multiple enclosed service entrance conductors |
|
|
Termination compartment service entrance arrangements |
|
|
Termination cabinet for 1 set of cable |
|
|
Clearances between gas facilities and electric meters |
|
|
Clearances between objects and electric meters |
Specs
| SPEC # | DESCRIPTION |
|
Placing Plants, Shrubbery or Structures around pad-mounted devices |
|
|
Customer Installed Precast Manhole |
|
|
Customer Installed Duct System |
|
|
Customer Installed Three-Phase Pad-Mounted Precast Transformer Foundation. 75KVA to 2500KVA Capacity |
|
|
Customer Installed Transformer Vault. 30KVA to 2500KVA Capacity |
|
|
Installation Instructions for Customer Installed Conduit Systems on PPL Terminal Poles |
|
|
Customer Low-Voltage Switchboards. Service Cable Terminal Compartment. |
|
|
Installation Instructions for 3-Phase, 200 Amp Switchgear Foundation |
|
|
Installation Instructions for 3-Phase, 600 Amp Switchgear Foundation |
|
|
Three-Phase Pad-Mounted Manual or Automatic Source Transfer Switch |
|
|
PPL EU Ultra Service Park Typical Utility Plan |
Primary - Overhead 12kV
These sketches provide rules for primary overhead 12kV service. Specifications for overhead service are at the bottom of this section.
Specs
| SPEC # | DESCRIPTION |
|
12 kV 3-Phase Service - Electronic Controlled Recloser - On Customer Owned Pole. Overhead supply to overhead. |
|
|
12 kV 3 Phase Service Fused Interrupter Switch on Customer-Owned Pole. Overhead Supply to Underground. |
|
|
12 kV 3 Phase Service Fused Interrupter Switch on Customer-Owned Pole. Overhead supply to overhead. |
|
|
7.2 kV Single Phase Service Fused Interrupter Switch and Metering on Customer-Owned Pole. OH supply to OH or UG |
|
|
12 kV 3 Phase Service Metering on Customer-Owned Pole. Overhead supply to overhead. |
|
|
12 kV 3 Phase Service Metering on Customer-Owned Pole. Overhead supply to underground |
|
| 6-09-200 | 7.2kV Single Phase Service Metering on Customer-Owned Pole Overhead Supply to Overhead or Underground |
Primary - Underground 12kV
Specs
| SPEC # | DESCRIPTION |
|
7,200/12,470V Service Termination and Metering Compartments in Customer-Owned Switchgear |
|
|
Customer Installed Precast Manhole |
|
|
Customer Installed Duct System |
|
|
Installation Instructions for Customer Installed Conduit Systems on PPL Terminal Poles |