Distributed Energy Resources (DER) Interconnection General Info
Getting Started
We want to make it easy for you to understand safety regulations and to apply to connect renewable energy projects to the grid.
DER Resources
Renewable Energy Pre-Application Renewable Energy Application Manual Application Instructions Interconnection Process/DER Checklist DER Interconnection Application Guide Transformer Loading for DER Customers Smart Inverter Website Net Metering and Virtual Net Metering PUC Net Metering Requirements Technical Requirements DER Inspection Information Renewable Energy Customer Billing and Usage Frequently Asked Questions DER Management Resources
Our Interconnections team is here to help with any questions or concerns you may have regarding both new and existing DER applications. Please contact the appropriate group below, based on your project details:
- Systems less than 25 kW, single-phase, email EUSolarPower@pplweb.com.
- Systems 25 kW and greater, single-phase and all three-phase systems less than 250 kW, email BusinessAccounts@pplweb.com.
- Systems 250 kW and greater, email DERApplications@pplweb.com.
Interconnection Meeting Workshop - November 6, 2024
Our most recent developer workshop is available. Topics discussed include the interconnection process, pre-applications, web resources and more. Download the presentation here .